It takes 15 electricians 24 days to wire a new housing subdivision. How many days would 18 electricians take to do the same job, assuming all electricians work at the same pace?
Accepted Solution
A:
So to set up this equation, you have to do Time1*Workers1=Time2*Workers2 In this case, Time1=24 days, Workers1=15 electricians, and Workers2=18 electricians, and we have to solve for Time2